Tasks completed:
-Went over SRS feedback (Team, 30 minutes)
-Decided on using tango icon library for remote icons. This will allow for easy -recognition by the user (Suggested by Matt Broadstone)
-Went through user walk through of our prototype. Got some good feedback (James / Adim, 30 minutes)

Next week's tasks:
-Design Document (Pat will start the doc, team will complete, ~2 hours)
-Build on existing prototype (James, 2 hours)
-Work on mobile web interface (Adim, 1 hour)

Problems:
None so far!