Wednesday, May 13, 2009

Project Complete

The title says it all.

Project was submitted and presented during week 10

Friday, May 8, 2009

Week 9 Status Report

Week 9 Status Report
Tasks completed:
-Compiled user testing data from week 8 testing (Pat, James : 90 minutes)
-Built PowerPoint presentation for Monday's demo (team : 120 minutes)
-Polished off application for submission (Pat, James : 60 minutes)

Next week's tasks:
-Submit project (team)
-Presentation

Problems:
Still going well, no serious problems.

Saturday, May 2, 2009

Week 8 Status Report

Week 8 Status Report
Tasks completed:
-Built user walkthrough surveys and scripts (1.5 hours) Pat, Adim, James
-Performed 10 walkthroughs (3 hours) Pat, Adim, James

Next week's tasks:
-Submit project (team)

Problems:
Still going well, no serious problems.